Luxembourg – Thionville: no trains from Thursday 16 July 2026 to Sunday 23 August 2026 inclusive
Alternatives put in place
Due to uncertainties related to road traffic, the CFL ask customers to allow an increase in travel time of approximately 45 minutes between Thionville and Luxembourg.
- Bus L90 Luxembourg (Gare Rocade) – Bettembourg – Hettange-Grande – Thionville
- The buses serve all stops usually served by train to/from Thionville
- Peak hours: departure every 30 minutes
- Off-peak hours: departure every hour
- Morning peak: additional departures from Hettange-Grande towards Luxembourg
- Bus L91 Luxembourg (Gare Rocade) – Howald, PE Howald – Thionville (direct)
- Departure every 20 to 30 minutes (Monday to Friday)
- Hourly departures (Saturday)
- During peak hours, some L91 buses operate only between Thionville and PE Howald
- Bus L92 (direct) Luxembourg (Gare Rocade) – Thionville
- Peak hours only: departures every 5 to 10 minutes
- TGV bus (reserved for TGV customers)
- According to TGV timetable for departures from Metz station
More information:
The Howald intermodal hub on the home straight
Following completion of the new platform at Howald and the commissioning of both platforms since March 2026, works at this new rail hub in the south of the capital are now entering the final phase.
The summer period will allow the installation of two escalators of 24 tonnes per platform, facilitating access to the tram/bus interchange spanning the railway tracks. Works on platform canopies will also be completed.
The closure will also enable completion of access paths reserved for CFL staff for maintenance purposes.
Full commissioning of the Howald intermoldal hub, including the bus station and tram stop, is scheduled for the last quarter of 2026.
Construction of the new Luxembourg – Bettembourg line continues
Works are also continuing on the new additional line between Luxembourg and Bettembourg, with commissioning planned from September 2027.
The closure period will allow platform works on a final 250-metre section north of Bettembourg station. These works are part of preparations for connecting the new line at Bettembourg station in 2027.
They include works on the substructure between natural ground and ballast, crucial for track stability, as well as installation of drainage systems to evacuate rainwater.
The closure will also enable installation of an underpass north of Bettembourg station connecting the two sides of the town beneath the tracks.
In parallel, works will continue on power supply (overhead lines) and signalling systems.
The new line is part of the CFL Group’s strategic projects to significantly increase network capacity on its busiest section.
Track renewal on various sections
Tracks will be renewed between Livange and Berchem over 300 metres, including: 1,280 m of rails, more than 1,000 sleepers, 1,800 tonnes of ballast.Further sleeper replacements will take place between Bettembourg and Dudelange over 450 metres.